首页 / 专利库 / 检验与质量控制 / 混凝土坍落度 / Method for surfacing poured material

Method for surfacing poured material

阅读:49发布:2021-12-26

专利汇可以提供Method for surfacing poured material专利检索,专利查询,专利分析的服务。并且A method for surfacing poured concrete material to make a slab with less manual labor and more strength by vibrating a straight edge guided at the proper height and supported on the building structure. The apparatus comprises vibrating straight edge for surfacing low slump concrete mix with less manual effort.,下面是Method for surfacing poured material专利的具体信息内容。

1. In a method for constructing a slab of synthetic material, such as concrete, at a predetermined elevation vertically spaced above a supporting surface, including the steps of: a. providing a plurality of laterally spaced support columns extending vertically upward from said supporting surface; b. supporting a material retaining floor form means between said vertically extending support columns adjacent said predetermined elevation above said supporting surface and below the ends of said columns; c. clamping laterally spaced guide rails onto said vertically extending support columns in substantially parallel relationship and at a predetermined vertically spaced elevation above said floor form means and independent of said form supporting means; d. pouring onto said floor form means an amount of workable synthetic materiaL sufficient to construct said slab; e. supporting a straight edge means from said guide rails at a position over and adjacent said poured material; and, f. manipulating said straight edge means along said guide rails into contact with and against said poured material a sufficient amount to work the top surface of said poured material to a predetermined elevation.
2. In a method for constructing a slab of synthetic material as described in claim 1 further including the step of, power vibrating said straight edge means while working the top surface of said poured material to said predetermined elevation.
3. In a method for constructing a slab of synthetic material as described in claim 1 further including the step of, adjusting the elevation of said spaced guide rails independent of said form support means.
4. In a method for constructing a series of vertically spaced slabs of synthetic material, such as concrete, with each of said slabs being located at a predetermined elevation above a supporting surface, including the steps of: a. providing a plurality of laterally spaced support columns extending vertically upward from said supporting surface; b. supporting a material retaining floor form means between said vertically extending support columns adjacent a first predetermined elevation above said supporting surface and below the ends of said columns; c. clamping laterally spaced guide rails onto said vertically extending support columns in substantially parallel relationship and at a predetermined vertically spaced distance above said floor form means and independent of said form supporting means; d. pouring onto said floor form means an amount of workable synthetic material sufficient to construct said slab; e. supporting a straight edge means from said guide rails at a position over and adjacent said poured material; f. manipulating said straight edge means along said guide rails into contact with and against said poured material a sufficient amount to work the top surface of said poured material to a first predetermined elevation; g. extending said laterally spaced vertical support columns above said first predetermined elevation to a second predetermined elevation; h. supporting a material retaining floor form means between said extended vertical support columns adjacent said second predetermined elevation; i. repeating steps (c-f) until a second slab is constructed at said second predetermined elevation; and, j. repeating steps (g-i) until the desired number of vertically spaced slabs are constructed.
5. In a method for constructing a series of slabs of synthetic material as described in claim 4 further including the step of power vibrating said straight edge means while working the top surface of said poured material to said series of predetermined elevations.
6. In a method for constructing a series of slabs of synthetic material as described in claim 4 further including the step of, adjusting the elevation of said guide rails independent of said form support means at each of said predetermined elevations.
说明书全文
高效检索全球专利

专利汇是专利免费检索,专利查询,专利分析-国家发明专利查询检索分析平台,是提供专利分析,专利查询,专利检索等数据服务功能的知识产权数据服务商。

我们的产品包含105个国家的1.26亿组数据,免费查、免费专利分析。

申请试用

分析报告

专利汇分析报告产品可以对行业情报数据进行梳理分析,涉及维度包括行业专利基本状况分析、地域分析、技术分析、发明人分析、申请人分析、专利权人分析、失效分析、核心专利分析、法律分析、研发重点分析、企业专利处境分析、技术处境分析、专利寿命分析、企业定位分析、引证分析等超过60个分析角度,系统通过AI智能系统对图表进行解读,只需1分钟,一键生成行业专利分析报告。

申请试用

QQ群二维码
意见反馈